{"status":"ok","message-type":"work","message-version":"1.0.0","message":{"indexed":{"date-parts":[[2026,5,2]],"date-time":"2026-05-02T07:00:02Z","timestamp":1777705202147,"version":"3.51.4"},"reference-count":23,"publisher":"SAGE Publications","issue":"4","content-domain":{"domain":[],"crossmark-restriction":false},"short-container-title":["IFS"],"published-print":{"date-parts":[[2024,4,18]]},"abstract":"<jats:p>\u00a0Distributed flexible flowshop scheduling is getting more important in the large-scale panel furniture industry. It is vital for a higher manufacturing efficiency and economic profit. The distributed scheduling problem with lot-streaming in a flexible flow shop environment is investigated in this work. Furthermore, the actual constraints of packaging collaborative and machine setup times are considered in the proposed approach. The average order waiting time for packaging and average order delay rate is used as objectives. Non-dominated sorting method is used to handle this bi-objective optimization problem. An improved encoding method was proposed to address the large-scale orders that need to be divided into sub-lots based on genetic algorithm. The proposed approach is firstly validated by benchmark with other multi-objectives evolutionary algorithms. The results found that the proposed approach had a good convergence and diversity. Besides, the influence of the proportion of large-scale orders priority level and sub-lot size was investigated in a panel furniture manufacturing scenario. The results can be concluded that the enterprise could obtain shorter order average waiting time and delay rate when the sub-lot sizes were set as two and the order priority level was allocated in the proportion of 1:2:3:4:5.<\/jats:p>","DOI":"10.3233\/jifs-237378","type":"journal-article","created":{"date-parts":[[2024,2,20]],"date-time":"2024-02-20T11:19:58Z","timestamp":1708427998000},"page":"8697-8707","source":"Crossref","is-referenced-by-count":0,"title":["Investigation on distributed scheduling with lot-streaming considering setup time based on NSGA-II in a furniture intelligent manufacturing"],"prefix":"10.1177","volume":"46","author":[{"given":"Jinxin","family":"Wang","sequence":"first","affiliation":[{"name":"College of Materials Science and Engineering, Nanjing Forestry University, Nanjing, China"}]},{"given":"Zhanwen","family":"Wu","sequence":"additional","affiliation":[{"name":"College of Materials Science and Engineering, Nanjing Forestry University, Nanjing, China"}]},{"given":"Longzhi","family":"Yang","sequence":"additional","affiliation":[{"name":"Department of Computer and Information Sciences, Northumbria University, Newcastle upon Tyne, UK"}]},{"given":"Wei","family":"Hu","sequence":"additional","affiliation":[{"name":"College of Materials Science and Engineering, Nanjing Forestry University, Nanjing, China"}]},{"given":"Chaojun","family":"Song","sequence":"additional","affiliation":[{"name":"College of Materials Science and Engineering, Nanjing Forestry University, Nanjing, China"}]},{"given":"Zhaolong","family":"Zhu","sequence":"additional","affiliation":[{"name":"College of Furnishings and Industrial Design, Nanjing Forestry University, Nanjing, China"}]},{"given":"Xiaolei","family":"Guo","sequence":"additional","affiliation":[{"name":"College of Materials Science and Engineering, Nanjing Forestry University, Nanjing, China"}]},{"given":"Pingxiang","family":"Cao","sequence":"additional","affiliation":[{"name":"College of Materials Science and Engineering, Nanjing Forestry University, Nanjing, China"}]}],"member":"179","reference":[{"key":"10.3233\/JIFS-237378_ref1","doi-asserted-by":"crossref","first-page":"433","DOI":"10.1007\/s10086-017-1643-2","article-title":"Current state and development trend of Chinesefurniture industry","volume":"63","author":"Xiong","year":"2017","journal-title":"Journal of Wood Science"},{"issue":"1","key":"10.3233\/JIFS-237378_ref2","doi-asserted-by":"crossref","first-page":"35","DOI":"10.1007\/BF00193874","article-title":"Stability of cabinet furniturebacking boards","volume":"28","author":"Smardzewski","year":"1993","journal-title":"Wood Science and Technology"},{"key":"10.3233\/JIFS-237378_ref3","doi-asserted-by":"crossref","first-page":"477","DOI":"10.5220\/0007768904770482","article-title":"Multi-agent ManufacturingExecution System (MES): Concept, architecture & ML algorithm for asmart factory case","author":"Mantravadi","year":"2019","journal-title":"21st International Conference on EnterpriseInformation Systems"},{"key":"10.3233\/JIFS-237378_ref4","first-page":"69","article-title":"A data-driven schedulingapproach to smart manufacturing","volume":"15","author":"Rossit","year":"2019","journal-title":"Journal of IndustrialInformation Integration"},{"key":"10.3233\/JIFS-237378_ref5","doi-asserted-by":"crossref","first-page":"1009","DOI":"10.1016\/j.procir.2018.03.272","article-title":"Smart manufacturing executionsystems for small and medium-sized enterprises","volume":"72","author":"Menezes","year":"2018","journal-title":"Procedia CIRP"},{"key":"10.3233\/JIFS-237378_ref6","doi-asserted-by":"crossref","first-page":"111","DOI":"10.1016\/j.mfglet.2017.12.005","article-title":"Scheduling research contributions toSmart manufacturing","volume":"15","author":"Rossit","year":"2018","journal-title":"Manufacturing Letters"},{"key":"10.3233\/JIFS-237378_ref7","doi-asserted-by":"crossref","first-page":"1005","DOI":"10.1007\/s00226-013-0554-7","article-title":"Production andproperties of wood-welded panels made from two Canadian hardwoods","volume":"47","author":"Belleville","year":"2013","journal-title":"Wood Science and Technology"},{"issue":"6","key":"10.3233\/JIFS-237378_ref8","doi-asserted-by":"crossref","first-page":"3818","DOI":"10.1109\/TCYB.2022.3164165","article-title":"Solving biobjective distributed flow-shop schedulingproblems with lot-streaming using an improved Jaya algorithm,-https:\/\/","volume":"53","author":"Pan","year":"2022","journal-title":"IEEE Transactions on Cybernetics"},{"issue":"2","key":"10.3233\/JIFS-237378_ref9","doi-asserted-by":"crossref","first-page":"219","DOI":"10.1016\/S0305-0483(98)00042-5","article-title":"A review of schedulingresearch involving setup considerations","volume":"27","author":"Allahverdi","year":"1999","journal-title":"Omega"},{"issue":"18","key":"10.3233\/JIFS-237378_ref10","doi-asserted-by":"crossref","first-page":"5235","DOI":"10.1080\/00207540903121065","article-title":"A review of scheduling researchinvolving setup considerations","volume":"48","author":"Toptal","year":"2010","journal-title":"International Journal ofProduction Research"},{"issue":"2","key":"10.3233\/JIFS-237378_ref11","doi-asserted-by":"crossref","first-page":"364","DOI":"10.1016\/j.eswa.2005.04.009","article-title":"An adaptive genetic algorithm withdominated genes for distributed scheduling problems","volume":"29","author":"Chan","year":"2005","journal-title":"ExpertSystems with Applications"},{"key":"10.3233\/JIFS-237378_ref12","first-page":"351","article-title":"A modified genetic algorithm fordistributed scheduling problems","volume":"14","author":"Jia","year":"2003","journal-title":"Journal of IntelligentManufacturing"},{"issue":"6","key":"10.3233\/JIFS-237378_ref13","doi-asserted-by":"crossref","first-page":"1846","DOI":"10.1109\/TNET.2009.2021609","article-title":"Low-complexity distributed scheduling algorithms for wireless networks","volume":"17","author":"Gupta","year":"2009","journal-title":"IEEE\/ACM Transactions on Networking"},{"key":"10.3233\/JIFS-237378_ref14","doi-asserted-by":"crossref","first-page":"105482","DOI":"10.1016\/j.cor.2021.105482","article-title":"Effective constructive heuristics fordistributed no-wait flexible flow shop scheduling problem","volume":"136","author":"Shao","year":"2021","journal-title":"Computers & Operations Research"},{"key":"10.3233\/JIFS-237378_ref15","doi-asserted-by":"crossref","first-page":"813","DOI":"10.1007\/s10479-018-2969-x","article-title":"Multi-objective genetic algorithm forenergy-efficient hybrid flow shop scheduling with lot streaming","volume":"290","author":"Chen","year":"2020","journal-title":"Annals of Operations Research"},{"key":"10.3233\/JIFS-237378_ref17","doi-asserted-by":"publisher","DOI":"10.1007\/978-3-642-80784-8_7"},{"issue":"4","key":"10.3233\/JIFS-237378_ref18","doi-asserted-by":"crossref","first-page":"754","DOI":"10.1016\/j.cor.2009.06.019","article-title":"The distributed permutation flowshopscheduling problem","volume":"37","author":"Naderi","year":"2010","journal-title":"Computers & Operations Research"},{"key":"10.3233\/JIFS-237378_ref19","first-page":"1483","article-title":"Production scheduling problem in a factory ofautomobile component primer painting","volume":"31","author":"Singgih","year":"2020","journal-title":"Journal of IntelligentManufacturing"},{"issue":"1","key":"10.3233\/JIFS-237378_ref20","doi-asserted-by":"crossref","first-page":"67","DOI":"10.5267\/j.ijiec.2018.4.001","article-title":"A review of scheduling problem and resolutionmethods in flexible flow shop","volume":"10","author":"Lee","year":"2019","journal-title":"International Journal ofIndustrial Engineering Computations"},{"key":"10.3233\/JIFS-237378_ref21","doi-asserted-by":"crossref","first-page":"100804","DOI":"10.1016\/j.swevo.2020.100804","article-title":"A distributed heterogeneous permutation flowshopscheduling problem with lot-streaming and carryoversequence-dependent setup time","volume":"60","author":"Meng","year":"2021","journal-title":"Swarm and EvolutionaryComputation"},{"issue":"1-2","key":"10.3233\/JIFS-237378_ref22","doi-asserted-by":"crossref","first-page":"331","DOI":"10.1016\/S0360-8352(02)00078-5","article-title":"Integrated process planning andscheduling with minimizing total tardiness in multi-plants supplychain","volume":"43","author":"Moon","year":"2002","journal-title":"Computers & Industrial Engineering"},{"issue":"12","key":"10.3233\/JIFS-237378_ref23","doi-asserted-by":"crossref","first-page":"3625","DOI":"10.1080\/00207543.2012.756151","article-title":"Two-stage assembly flow-shop scheduling problemwith non-identical assembly machines considering setup times","volume":"51","author":"Mozdgir","year":"2013","journal-title":"International Journal of Production Research"},{"issue":"2","key":"10.3233\/JIFS-237378_ref24","doi-asserted-by":"crossref","first-page":"225","DOI":"10.1162\/evco.2008.16.2.225","article-title":"Multiobjective immune algorithm with nondominatedneighbor-based selection","volume":"16","author":"Gong","year":"2008","journal-title":"Evolutionary Computation"}],"container-title":["Journal of Intelligent &amp; Fuzzy Systems"],"original-title":[],"link":[{"URL":"https:\/\/content.iospress.com\/download?id=10.3233\/JIFS-237378","content-type":"unspecified","content-version":"vor","intended-application":"similarity-checking"}],"deposited":{"date-parts":[[2026,4,29]],"date-time":"2026-04-29T09:43:11Z","timestamp":1777455791000},"score":1,"resource":{"primary":{"URL":"https:\/\/journals.sagepub.com\/doi\/full\/10.3233\/JIFS-237378"}},"subtitle":[],"short-title":[],"issued":{"date-parts":[[2024,4,18]]},"references-count":23,"journal-issue":{"issue":"4"},"URL":"https:\/\/doi.org\/10.3233\/jifs-237378","relation":{},"ISSN":["1064-1246","1875-8967"],"issn-type":[{"value":"1064-1246","type":"print"},{"value":"1875-8967","type":"electronic"}],"subject":[],"published":{"date-parts":[[2024,4,18]]}}}