{"status":"ok","message-type":"work","message-version":"1.0.0","message":{"indexed":{"date-parts":[[2026,4,21]],"date-time":"2026-04-21T04:13:44Z","timestamp":1776744824491,"version":"3.51.2"},"reference-count":54,"publisher":"IGI Global","issue":"3","content-domain":{"domain":[],"crossmark-restriction":false},"short-container-title":[],"published-print":{"date-parts":[[2013,7,1]]},"abstract":"<p>The growing rate of delays in project delivery is considered a major criticism of the construction companies in the United Arab Emirates (UAE). This paper aims to investigate the causes and effects behind the delays pertaining to delivery of construction projects in the UAE. The study is exploratory in nature, and incorporates a pilot questionnaire survey and interviews. An extensive literature review indicates potential factors that have possible effects on construction completion delay. The questionnaire forms were sent to 50 construction companies. Thirty-five (70%) completed responses were received. Analysis of the survey data has revealed that about 42 potential causes and effects of delay relate to various groups of stakeholders. The results show the top fifteen factors relate to clients, project managers and finance aspects. It was found that cost and time overruns are the most significant effects. These results are in partial agreement with previous studies. The paper argues that the key determinant in ensuring project control is on-time project delivery. The results of the study can provide moderate support for a suggested hypothesis, through a framework of project success factors. It should be of high concern to knowledge managers in various roles and decision-makers.<\/p>","DOI":"10.4018\/jitpm.2013070104","type":"journal-article","created":{"date-parts":[[2013,8,19]],"date-time":"2013-08-19T13:08:45Z","timestamp":1376917725000},"page":"50-65","source":"Crossref","is-referenced-by-count":21,"title":["An Investigation into the Risk of Construction Projects Delays in the UAE"],"prefix":"10.4018","volume":"4","author":[{"given":"Omayma","family":"Motaleb","sequence":"first","affiliation":[{"name":"The Scott Sutherland School of Architecture and Built Environment, Robert Gordon University, Aberdeen, UK"}],"role":[{"role":"author","vocabulary":"crossref"}]},{"given":"Mohammed","family":"Kishk","sequence":"additional","affiliation":[{"name":"The Scott Sutherland School of Architecture and Built Environment, Robert Gordon University, Aberdeen, UK"}],"role":[{"role":"author","vocabulary":"crossref"}]}],"member":"2432","reference":[{"key":"jitpm.2013070104-0","doi-asserted-by":"publisher","DOI":"10.1061\/(ASCE)0733-9364(2008)134:11(831)"},{"key":"jitpm.2013070104-1","doi-asserted-by":"publisher","DOI":"10.1061\/(ASCE)0733-9364(2006)132:2(125)"},{"key":"jitpm.2013070104-2","doi-asserted-by":"publisher","DOI":"10.1057\/rlp.2009.11"},{"key":"jitpm.2013070104-3","unstructured":"Abu Dhabi Chamber of Commerce. (2009). Retrieved May10, 2011, from http:\/\/www.abudhabichamber.ae\/"},{"issue":"3","key":"jitpm.2013070104-4","first-page":"81","article-title":"Delay in building construction projects in developing countries: A case study of Nepal.","volume":"10","author":"N.Acharya","year":"2005","journal-title":"Journal of the Korean Society of Maintenance Engineers"},{"key":"jitpm.2013070104-5","unstructured":"Ahmed, S., Azhar, S., Kappagantula, P., & Gollapudi, D. (2003). Delays in construction: A brief study of the Florida construction industry. In ASC Proceeding of the 39th Annual Conference, Clemson University, Clemson, SC (pp. 257-266)."},{"key":"jitpm.2013070104-6","doi-asserted-by":"publisher","DOI":"10.1016\/S0263-7863(02)00028-5"},{"key":"jitpm.2013070104-7","doi-asserted-by":"publisher","DOI":"10.1061\/(ASCE)0733-9364(2006)132:7(667)"},{"key":"jitpm.2013070104-8","doi-asserted-by":"publisher","DOI":"10.1016\/S0263-7863(98)00060-X"},{"key":"jitpm.2013070104-9","doi-asserted-by":"publisher","DOI":"10.1061\/(ASCE)CO.1943-7862.0000154"},{"key":"jitpm.2013070104-10","doi-asserted-by":"publisher","DOI":"10.1108\/09699980710731308"},{"key":"jitpm.2013070104-11","doi-asserted-by":"publisher","DOI":"10.1016\/S0925-5273(01)00177-3"},{"key":"jitpm.2013070104-12","unstructured":"APM. (2006). APM body of knowledge (5th ed.). ISBN-1-903494-25-7."},{"key":"jitpm.2013070104-13","unstructured":"Arain, F. (2005). A framework for developing a knowledge-based decision supports system for management of variations order for institutional buildings. Retrieved July 29, 2011, from http:\/\/www.itcon.org\/data\/works\/att\/2006_21.content.04149.pdf"},{"key":"jitpm.2013070104-14","doi-asserted-by":"publisher","DOI":"10.1016\/j.ijproman.2005.08.005"},{"key":"jitpm.2013070104-15","unstructured":"Asnaashari, S., Farahani, S., Hoseini, A., Knight, A., & Hurst, A. (2009, May). Causes of delay in Iran construction projects. In Proceedings of the 5th International Conference on Construction in the 21st Century (CITC-V), Istanbul, Turkey."},{"key":"jitpm.2013070104-16","doi-asserted-by":"publisher","DOI":"10.1016\/j.ijproman.2005.11.010"},{"key":"jitpm.2013070104-17","doi-asserted-by":"publisher","DOI":"10.1163\/157302510X504953"},{"key":"jitpm.2013070104-18","unstructured":"Choudhury, I., & Phatak, O. (2004, April). Correlates of time overrun in commercial construction. In ASC Proceedings of the 40th Annual Conference, Brigham Young University - Provo, Utah."},{"key":"jitpm.2013070104-19","author":"S. J.Coakes","year":"2009","journal-title":"SPSS version 15.0 for windows: Analysis without Anguish"},{"key":"jitpm.2013070104-20","doi-asserted-by":"publisher","DOI":"10.1061\/(ASCE)0733-9364(2001)127:5(419)"},{"key":"jitpm.2013070104-21","unstructured":"Ellis, R., & Thomas, H. (2003). The root causes of delays in highway construction. In Proceedings of the 82nd Annual Meeting of the Transportation Research Board, Washington DC."},{"key":"jitpm.2013070104-22","unstructured":"Elweshahy, M. (2008, September). Construction management guide. Retrieved April 20, 2011, from http:\/\/cmguide.org\/archives\/39"},{"key":"jitpm.2013070104-23","doi-asserted-by":"publisher","DOI":"10.1108\/13664380910977592"},{"key":"jitpm.2013070104-24","doi-asserted-by":"publisher","DOI":"10.1080\/01446190600827033"},{"key":"jitpm.2013070104-25","doi-asserted-by":"publisher","DOI":"10.1016\/j.buildenv.2005.01.004"},{"key":"jitpm.2013070104-26","doi-asserted-by":"publisher","DOI":"10.1016\/S0263-7863(02)00055-8"},{"key":"jitpm.2013070104-27","unstructured":"Global Real State News Centre. (2009). Retrieved May15,2011from http:\/\/www.realestatechannel.com\/international-markets\/residential-real-estate\/dubai-construction-uae-real-estate-emil-rademeyer-proleads-global-alma-kadragic-429.php"},{"issue":"5","key":"jitpm.2013070104-28","doi-asserted-by":"crossref","first-page":"522","DOI":"10.1016\/j.ijproman.2008.07.003","article-title":"Cost escalation and schedule delays in road construction projects in Zambia.","volume":"127","author":"C.Kaliba","year":"2008","journal-title":"International Journal of Project Management"},{"issue":"2","key":"jitpm.2013070104-29","doi-asserted-by":"crossref","first-page":"53","DOI":"10.1080\/15623599.2010.10773144","article-title":"Causes of delays in Iranian construction projects.","volume":"10","author":"M.Khoshgoftar","year":"2010","journal-title":"The International Journal of Construction Management"},{"key":"jitpm.2013070104-30","author":"N. T.Kottegoda","year":"1997","journal-title":"Statistics, probability, and reliability for civil and environmental engineers"},{"key":"jitpm.2013070104-31","doi-asserted-by":"publisher","DOI":"10.1108\/09699980410527867"},{"key":"jitpm.2013070104-32","doi-asserted-by":"publisher","DOI":"10.1080\/0144619042000326710"},{"key":"jitpm.2013070104-33","doi-asserted-by":"publisher","DOI":"10.1007\/s12205-008-0367-7"},{"key":"jitpm.2013070104-34","unstructured":"Low, S., Pheng, L. J., Ying, & Tan, I. (2009). PSSCOC and causes of construction delays in Singapore and four selected Asian countries. International Construction Law Review, 26(3)."},{"key":"jitpm.2013070104-35","unstructured":"Majid, I. A. (2006). Causes and effects of delay in Aceh construction industry. Unpublished Master thesis, University Technology Malaysia."},{"key":"jitpm.2013070104-36","doi-asserted-by":"publisher","DOI":"10.1016\/S0263-7863(02)00027-3"},{"key":"jitpm.2013070104-37","unstructured":"Menesi, W. (2007). Construction delays analysis under multiple baseline updates. Unpublished Master thesis, the University of Waterloo."},{"key":"jitpm.2013070104-38","doi-asserted-by":"publisher","DOI":"10.1680\/mop.16934"},{"key":"jitpm.2013070104-39","unstructured":"Motaleb, O. H. (2009). An investigation into the causes, effects and handling of construction delays in the United Arab Emirates. Unpublished Master thesis, the Robert Gordon University, Aberdeen."},{"key":"jitpm.2013070104-40","author":"A.Noulmanee","year":"2000","journal-title":"Internal causes of delays in highway construction projects in Thailand"},{"key":"jitpm.2013070104-41","doi-asserted-by":"publisher","DOI":"10.1016\/S0263-7863(00)00037-5"},{"key":"jitpm.2013070104-42","doi-asserted-by":"publisher","DOI":"10.1108\/09699980610690756"},{"key":"jitpm.2013070104-43","year":"2004","journal-title":"A guide to project management body of knowledge"},{"key":"jitpm.2013070104-44","doi-asserted-by":"publisher","DOI":"10.1016\/j.ijproman.2006.11.007"},{"key":"jitpm.2013070104-45","unstructured":"Sun, M., Sexton, M., Aouad, G., Fleming, A., Senaratne, S., & Anumba, C. \u2026 Yeoh, M. (2004). Managing changes in construction projects. Retrieved April 14, from http:\/\/www.bne.uwe.ac.uk\/cprc\/publications\/mcd.pdf"},{"key":"jitpm.2013070104-46","doi-asserted-by":"publisher","DOI":"10.1016\/j.ijproman.2007.09.009"},{"key":"jitpm.2013070104-47","author":"J.Theodore","year":"2009","journal-title":"Construction delay"},{"key":"jitpm.2013070104-48","unstructured":"Tumi, S., Omran, A., & Pakir, A. (2009, November). Causes of delay in construction industry in Libya. In Proceedings of the International Conference on Economics and Administration (ICEA\u2013 FAA), University of Bucharest, Romania."},{"key":"jitpm.2013070104-49","unstructured":"United Nations Development Group. (2010, March). (1st Quarter). Iraq Trust Fund Project#66992: C10-08. Retrieved from http:\/\/www.unesco.org\/fileadmin\/MULTIMEDIA\/FIELD\/Iraq\/pdf\/Reports\/Quarterly\/Fiche_C10-08_Samara_Al_Askari_Shrine_1st_Quarter_2010.pdf"},{"key":"jitpm.2013070104-50","unstructured":"Wiguna, I. A., & Scott, S. (2005). Analyzing the risks affecting construction delay and cost overruns in Indonesia building projects. Innovation in Architecture, Engineering and Construction, 841-849."},{"key":"jitpm.2013070104-51","unstructured":"World Bank Iraq Trust Fund Project. (2008, March). (1st Quarter). #: P 087907. Retrieved on January 20, 2011from http:\/\/siteresources.worldbank.org\/IRFFI\/Resources\/ConsolidatedITFPSSwithpagenos.pdf"},{"key":"jitpm.2013070104-52","doi-asserted-by":"publisher","DOI":"10.1016\/j.ijproman.2009.10.005"},{"key":"jitpm.2013070104-53","doi-asserted-by":"publisher","DOI":"10.1016\/j.ijproman.2006.02.006"}],"container-title":["International Journal of Information Technology Project Management"],"original-title":[],"language":"ng","link":[{"URL":"https:\/\/www.igi-global.com\/viewtitle.aspx?TitleId=80405","content-type":"unspecified","content-version":"vor","intended-application":"similarity-checking"}],"deposited":{"date-parts":[[2022,6,2]],"date-time":"2022-06-02T04:00:11Z","timestamp":1654142411000},"score":1,"resource":{"primary":{"URL":"https:\/\/services.igi-global.com\/resolvedoi\/resolve.aspx?doi=10.4018\/jitpm.2013070104"}},"subtitle":[""],"short-title":[],"issued":{"date-parts":[[2013,7,1]]},"references-count":54,"journal-issue":{"issue":"3","published-print":{"date-parts":[[2013,7]]}},"URL":"https:\/\/doi.org\/10.4018\/jitpm.2013070104","relation":{},"ISSN":["1938-0232","1938-0240"],"issn-type":[{"value":"1938-0232","type":"print"},{"value":"1938-0240","type":"electronic"}],"subject":[],"published":{"date-parts":[[2013,7,1]]}}}